Fit-outWorkplace · Olympia Tech Park, Guindy

A trading floor that had to stay quiet

An open analytics floor for 96 people, with acoustic separation good enough that a call desk and a quiet room can share a wall.

Client
Vantage Analytics
Area
12,400 sq ft
Programme
14 weeks
Completed
2025
PLAN · NOT TO SCALE

Plate 01 · Diagrammatic plan. Not a measured drawing.

01The brief

Vantage had outgrown two half-floors and taken a single 12,400 sq ft plate. The requirement was blunt: 96 desks, twelve meeting rooms, and no complaints about noise. Their previous office had glass boxes that leaked every word, and the team had stopped using them.

02What we did

We planned the floor as three acoustic zones rather than one open plan with rooms dropped into it. The dealing desks sit in the middle of the plate away from the façade; enclosed rooms line the two service cores; and the quiet zone occupies the far corner, reached without crossing the noisy centre.

Every enclosed room is built full-height, slab to slab, with a double-stud partition and mineral wool infill — not a partition stopped at the false ceiling, which is where most fit-out acoustics quietly fail. Glass is 12 mm laminated with an acoustic interlayer, and doors are 45 mm solid-core with drop seals.

The ceiling is a mix: exposed and painted over the open desks with suspended acoustic rafts for absorption, and plain gypsum over the rooms so the partitions could land on something solid. Post-handover sound testing measured 42–46 dB reduction between rooms and floor.

03Specification

Carpet area
12,400 sq ft
Density
96 workstations, 12 meeting rooms
Partitions
Full-height double-stud, 100 mm mineral wool
Glazing
12 mm laminated acoustic, butt-jointed
Ceiling
Exposed services + suspended acoustic rafts
Flooring
Carpet tile (desks), vinyl plank (circulation)
Measured attenuation
42–46 dB between enclosed rooms
Approvals
Landlord fit-out permit, fire NOC amendment

04Programme

  1. 01Survey to GFC4 weeks
  2. 02Civil & partitions5 weeks
  3. 03Services & ceiling4 weeks
  4. 04Furniture & snagging1 week

05Credits

Scope
Design, drawings, execution, handover
Services
MEP coordination by Modulo; HVAC by landlord contractor
Handover
On programme