Process
Five stages.Nothing hiddenbetween them.
Most interior projects go wrong in the gaps — between the designer and the contractor, between the quotation and the invoice, between handover and the snag that never got fixed. This is how we close them.
- Design to GFC
- 3–4 weeks
- Typical build
- 4–14 weeks
- Site reporting
- Weekly, with photos
- Return visit
- 90 days after handover
01
3–5 days
Measure
We survey the site ourselves. No relying on the builder's plan.
Two of us come with a disto and a camera. We record the actual slab-to-slab height, the beam drops, where the services really run, and every place the site disagrees with the drawing you were given. This is where the surprises get found — before the quotation, not during the build.
- You end up holding
- Measured drawing
- Services map
- Condition photographs
02
2–3 weeks
Draw
Two or three plan options, then one developed properly.
You see plans first, because the plan is the decision that matters. Once a plan is agreed we build it in 3D and put a physical material board in front of you — actual laminate chips and veneer samples, not a Pinterest board. Revisions are expected at this stage and are not billed extra.
- You end up holding
- Space plan options
- 3D views
- Physical material board
03
1 week
Specify
A drawing set and an itemised BOQ. The number stops moving here.
Good-for-construction drawings, an item-by-item bill of quantities, and a fixed-sum quotation against that scope. If the scope doesn't change, the number doesn't change. Variations are quoted in writing and signed before anyone starts them.
- You end up holding
- GFC drawing set
- Itemised BOQ
- Fixed-sum quotation
04
4–10 weeks
Make
Workshop and site run in parallel. You get a report every Friday.
Panels are cut and assembled at Thirumudivakkam while civil, electrical and ceiling work runs on site — which is why a modular kitchen can land in a week rather than living in your flat for a month. Every Friday you get photographs, percentage complete, and anything we need a decision on.
- You end up holding
- Weekly photo report
- Percentage-complete tracker
- RFI log
05
1 week + 90 days
Hand over
Snag list closed in writing, then we come back at 90 days.
We walk the space with you and write the snag list down; it isn't closed until you sign it off. You get as-built drawings, warranty documents and an operations file. Ninety days later we come back and re-check every hinge, channel and door — free, whether or not you called us.
- You end up holding
- Signed snag closure
- As-built set
- Warranty & O&M file
06Payment
Four instalments, and you hold the last one.
The final five percent is released only when you sign the snag closure sheet. It exists so that the last ten percent of a job — the part everybody in this industry is famous for abandoning — stays worth our while.
01
40%
Order confirmation
02
40%
Material delivery / workshop dispatch
03
15%
Installation complete
04
5%
Snag list signed off
Design fees are billed separately and in advance of the build. GST applies to all invoices. Variations are quoted in writing and approved by you before the work is started — never discovered afterwards.
07Documentation
Everything you're handed, by stage.
Survey
Measured drawing · Services & beam mapping · Condition report
Design
Space plan options · 3D views · Material & finish board
Tender
GFC drawing set · Itemised BOQ · Fixed-sum quotation
Build
Weekly site report · RFI log · Material approval sheets
Handover
As-built drawings · Warranty & O&M file · Snag closure sheet
Plate 03 · Section. Raised service platform shown in red.
Start at stage one.
A survey costs you nothing and tells us more than an hour of conversation. If the project isn't right for us, that's when we'll say so.